Joint Research Centre, Building 62C Customs- Ispra (Italy)

Joint Research Centre, Building 62C - Customs - Ispra (Italy)

ClientEuropean Commission

Work activitiesDetailed design

PlaceISPRA (ITALY)

VOLUME1400 m³

Period2016 - 2017

Overview

The project involves the construction of a building in the European research centre (JRC) located in the municipality of Ispra. The intervention consists of the total demolition of the existing building and its reconstruction through the construction of a main body (depot) with position, orientation and height similar to the current one, and to the South-West, of a lower lateral structure, attached, in which an office with toilets will be added. The new project involves the construction of a total internal volume (upper structure and lower structure) of around 1400 m³, thus a volume similar to the existing one. The parking area and the loading/unloading area in front of the driveway entrance will be covered by a shelter that will be built as a sort of portal that transversely crosses the whole building and is partially on top of it in a longitudinal direction.

Similar Projects

TEEM – Milan east external ring motorway (italy)

TEEEM – Milan east external ring motorway (italy)

ClientConsorzio Arco TEM S.p.A.

Work activitiesDetailed design

PlaceMILANO (ITALY)

Period2011 - 2012

Creditshttps://www.tangenziale.esterna.it/

Overview

Within the overall works associated to the East External Ring Motorway of Milan (TEEM), Alpina was responsible to develop several projects to improve road network interconnected to the new ring motorway system. Significant is the completion of the Motorway Cassanese S.P. n.103, from Cassina de Pecchi to Pozzuolo Martesana, that consists in the functional upgrade of the existing single road carriage into a motorway with two lanes per carriage: 2.5 km Motorway length, the Melzo and Pozzuolo Martesana junctions, one double viaduct (250 m), the Molgora river bridges, two fly-overs and several hydraulics works.

Similar Projects

A1/E35 Motorway – Four lanes functional upgrade section Milan sud – Lodi, 18 Km (Italy)

A1/E35 Motorway – Four lanes functional upgrade section Milan sud – Lodi, 18 Km (Italy)

ClientSPEA S.p.A.

Work activitiesDetailed design

PlaceLODI (ITALY)

Period2017- 2018

Overview

Detailed design of the functional upgrade to full four lanes of the existing motorway,  section from Milano Sud Junction (Km 4+852) to Lodi Junction (22+306), approximately 18 km.

The works includes the detailed design of the new four lanes motorway, the re-alignment of A50 interchange speed ramps, the Melegnano-Binasco junction, the A58 TEEM interchange, the Lodi junction, the S. Zenone gas station speed ramps,  five bridge extension (new decks and abutments) including the major one above  Lambro river, the extension of n°45 culverts of the secondary hydraulic system, the new road drainage system, the installation of acoustic barriers and safety barriers.  

Similar Projects

A7- A10 Motorway Genoa – San Benigno junction (ITALY)

A7- A10 Motorway Genoa - San Benigno junction (Italy)

ClientSPEA S.p.A.

Work activitiesPreliminary and Final design

PlaceGENOA (ITALY)

Period2018- 2019

Creditsautostrade.it

Overview

Engineering services for the Preliminary and Final design of the functional upgrade of the existing urban motorway junction at Genoa San Benigno – Lot 2 – Section D and E.

The services include the new horizontal and vertical alignment of existing S. Benigno junction ramps, connections with local roads, access to the main Port areas, the diversion of the existing railway line (120 m) and the design of new major structures: n°3 concrete viaducts, embankments & trenches, hydraulics works, site construction phases.

Similar Projects

BREBEMI Motorway (Italy)

BREBEMI Motorway (Italy)

ClientSocietà di Progetto Brebemi S.p.A.

Work activitiesDetailed design, Technical support for the approval, Verification of the final plan prepared by the General Contractor, Supervision of works

PlaceLombardy (ITALY)

Period2008-2013

Project value

Creditsbrebemi.it

Overview

The new motorway Brebemi crosses the Po Valley plain for approximately 49 km directly connecting Brescia and Milan.

The motorway structure provides for a platform of 2+2/3+3 flow-lanes plus an emergency lane in each direction.

The extent of the motorway of about 43,5 km results as running alongside the future Milano Verona high-speed railway line with which it shares many works (overpasses, underpasses, tunnels) included in so-called integrated works. Where it reaches the Adda Serio and Oglio rivers, there are three viaducts manufactured with segmental bridge technology with spans of up to 90 m.

Similar Projects

Ridracoli Dam Water System Forlì (Italy)

Ridracoli Dam Water System Forlì (Italy)

ClientRomagna Acque S.p.A

Work activitiesServices provided by Alpina: Preliminary design, Detailed design, Work Supervision

PlaceRIDRACOLI (ITALY)

Period1963 – 2001

Overview

The Romagna waterworks derives its waters from Ridracoli Lake located in the municipality of Bagno di Romagna (FO).An arch-gravity dam (103,5 high with a crest length of 432 m) is built on Bidente river.Purpose: water distribution to the associated municipalities such as Forlì, Cesena, Ravenna.

The project includes:

Type :    arch gravity dam

Total reservoir capacity :       33.000.000 m³
High :  106 m

Total concrete volume :  600.000 m³

High pressure pipe line:         33 km; 1.400 mm
Installed Power  :     7 MW

Water treatment Plant :    3,6 m³/s