Hone II Hydroelectric Power Plant

Hone (Italy)
CLIENT:
CVA
Work activities:
Detailed design
Place:
Hone (Italy)
Period:
2022 - 2024
 

Overview

Hone II hydro power plant is located in the Alps, within Valle d’Aosta region.
The project involves the complete refurbishment of the hydroelectric plant (which has been in operation for over 100 years).
The scope of work assigned to Alpina includes:

  • dam and intake on Brenve creek;
  • free surface hydraulic tunnel (diameter ~4,10m, length 4100m);
    forebay tank;
  • emergency overflow, consisting in a free surface channel;
    penstock (length 1350m; diameter DN1200mm-1000mm, head 770m);
  • powerhouse;
  • 2 turbine/generator units; total installed 40 MW;
  • 1 transformer unit with connection cables to the local electric network.
    environmental mitigation and monitoring measures.

The total cost of the works amounts to approximately 120 million euros.