The new bypass tunnel represents the main intervention of the works for the hydraulic safety of the Lake, with the primary purpose of evacuating flows even in case of landslide collapse obstructing the outlet river.
The route of the tunnel develops along the right orographic bank for approximately 1316 meters, with the entrance located about 180 meters northeast of the entrance of the current spillway tunnel, in the Municipality of Idro, and the exit situated in the municipality of Lavenone approximately 460 meters downstream of the existing outlet.
The structure is entirely external to the perimeter of the landslide on the left orographic side.
The tunnel can be divided into 3 sections:
Intake structure with a width of 22 meters.
Rectangular-type connecting structure with a double arch, approximately 32 meters in length, with dimensions of 4.50 + 4.50 meters in width and 4.50 meters in height.
The hydraulic tunnel has a polycentric internal section with an area of approximately 40 square meters and a constant slope of 0.85%.